Is it possible to show two dates on the calendar view? In our process, we have a Project Completion date and a Project Implementation date. Both dates are important, and it would be great to see them both in the Calendar view.
Is it possible? Is it something that can be added?
Thanks
Best answer by Lais Laudari
Hi @carl-bulls! Only 1 due date field will be considered (the last field filled in) in the Calendar view. As mentioned above you can use the card subtitles configuration to show the two dates you need on the cards.
Sorry about that, I thought it was possible to use two due dates on the same card to view on the calendar, but the calendar takes the last defined due date.
If it is just for your viewing, you can use the card subtitles configuration to show the two dates you need on the cards.
Hi @carl-bulls! Only 1 due date field will be considered (the last field filled in) in the Calendar view. As mentioned above you can use the card subtitles configuration to show the two dates you need on the cards.
Using the card subtitles to show my two dates is working well. I do have a question though. Is there any way to remove the “due date” tag/label in the subtitle? Right now, it automatically shows up. I only want to see the two dates as shown above. See @marcosmelo screenshot above for what i’m speaking of.
In fact, you can't remove the expiration date label. Since it is a due date field, it must generate this alert.
Unless you use a simple date and time field, which is not a due date field. Then it won't appear. But I think this could interfere with the calendar view.
Is it possible to show two dates on the calendar view? In our process, we have a Project Completion date and a Project Implementation date. Both dates are important, and it would be great to see them both in the Calendar view.
Is it possible? Is it something that can be added?
Thanks
Page 1 / 1
It's good idea. And the calculation field can be used to generate the planned Vs realized.
Sorry about that, I thought it was possible to use two due dates on the same card to view on the calendar, but the calendar takes the last defined due date.
If it is just for your viewing, you can use the card subtitles configuration to show the two dates you need on the cards.
Hi @carl-bulls! Only 1 due date field will be considered (the last field filled in) in the Calendar view. As mentioned above you can use the card subtitles configuration to show the two dates you need on the cards.
Using the card subtitles to show my two dates is working well. I do have a question though. Is there any way to remove the “due date” tag/label in the subtitle? Right now, it automatically shows up. I only want to see the two dates as shown above. See @marcosmelo screenshot above for what i’m speaking of.
In fact, you can't remove the expiration date label. Since it is a due date field, it must generate this alert.
Unless you use a simple date and time field, which is not a due date field. Then it won't appear. But I think this could interfere with the calendar view.